The groundbreaking of Reston Association’s Lake Thoreau pool renovations project has been delayed (via RA)

Two Reston pool projects are facing some delays.

The Ridge Heights Pool will open two weeks later than anticipated.

In a statement released Friday (April 29), Reston Association said the delay was prompted by “continuing supply chain delays and manufacturing shortages that have slowed repairs to the facility.”

Repairs include re-plastering of the previous pool surface layers, tile line and in-pool tile replacement, and coping stone replacement on the main and wading pools.

The pool will now open on May 28 instead of May 14. Lake Audubon Pool will open on May 14, along with the heated pool at North Shore.

RA noted that the scheduled opening is “pending supply and contractor availability and weather conditions.”

Raw materials like aggregate and binders are in high demand and short supply, according to Chris Schumaker, RA’s capital projects director. RA has been waiting several months for coping stones.

“RA is doing everything within its control to complete the Ridge Heights pool for a May 28 opening,” RA’s spokesperson Mike Leone told FFXnow.

RA has also delayed the groundbreaking of Lake Thoreau pool’s renovation to May. The $3.5 million project had an anticipated groundbreaking of October or November.

“Unfortunately, we do not have a more specific date. We are focused on a 2023 Memorial Day Weekend opening but it will be tight,” Leone said.

The opening timeframe could be pushed back if permitting delays continue. RA is currently working through the remaining county permits required for the project to proceed.

Key design elements of the renovation include ADA access with a ramp into the pool, a redesign of the overlook deck, pool reconstruction, expansion of the parking lot, and repositioning of the spa away from the bathhouses as well as modifying and expansion of said bathhouses.