Vienna approves more funds for new police station, as project nears finish

Construction on Vienna’s new police station is expected to be complete in July (staff photo by Angela Woolsey)

It will cost the Town of Vienna nearly $300,000 more to finish construction on its new police station at 215 Center Street South.

The Vienna Town Council agreed last week to authorize spending increases of $249,310 for contractor Hoar Construction and $48,817 for project manager Downey & Scott.

However, town officials emphasized that the overall project is still on track to come in $98,913 under the $17.3 million allocated to it from bond funding and cable fees.

“The police station has several different components to it,” Vienna Director of Finance Marion Serfass said at the May 2 meeting. “Some items are under the original budget, and some are over, but in total, the entire project is under budget by $98,000.”

One of the items that has gone over budget is Downey & Scott’s contract, which was originally approved in January 2019 with a $318,950 price tag.

Hired to manage the construction process, the firm previously requested and received an additional $67,680 in October, citing a longer-than-anticipated pre-construction phase and “unknown condition incidents” that emerged after work on the site began.

Bringing the firm’s bill up to $437,897, this new increase was needed to extend the contract by 90 days, according to a memo sent to the town on April 8.

“Due to supply chain disruptions, the roofing materials, fencing, and other materials have been delayed,” Downey & Scott said in the memo, reporting that Hoar’s estimated completion date for the project is July 19.

That will be “less than a month late despite historic issues with construction materials and the supply chain,” according to town staff.

The town council approved both funding requests without any public discussion, but members said they had talked about them in a closed conference session.

“I just want the public to know we discussed this in detail,” Councilmember Chuck Anderson said. “We asked a bunch of questions, so it’s not like we’re just automatically approving it.”

Construction on the Vienna Police Department’s new building began in January 2021. When completed, the station will be approximately 30,000 square feet in size with a firing range, additional interview rooms, more personnel and storage space, and a 1,500-square-foot multipurpose room that could be used by the community, among other amenities.

Recent Stories

Fairfax County is now bringing nature to residents’ doorsteps. Last week, the Fairfax County Park Authority launched a new, fully electric mobile nature center called the Wonder Wagon. The tricked-out…

A new pop-up store at Tysons Corner Center hopes to entice shoppers on the lookout for possible Mother’s Day gifts. Emilia George, a New York-based maternity lifestyle retailer, is running…

The Town of Herndon has granted Comstock a little more breathing room before the developer needs to move forward with its long-planned downtown overhaul. A two-year pause in construction that…

The Elden Street Tea Shop is almost ready to unveil its new location in Reston. After closing its original Herndon location in January, the business is set to reopen at…

Potomac Harmony is Back! Following a gap year of competing, then virtual rehearsals during the pandemic, followed by the well-earned retirement of our long-term director, a year of a director search, Potomac Harmony hit the regional contest stage in Concord, North Carolina in March for the first time since 2018! It was exhilarating, reaffirming, and rewarding!

The chorus hit all of its goals, the biggest of which was to have fun and sing our best on contest stage — we did both! Because we earned a score over 400 points, our new Director, Allison Lynskey, was awarded the Novice Director award, photo above. Additionally, one of our charter members, Jackie Bottash, was nominated for and honored with the Leadership Excellence award. It was a celebratory weekend!

What’s next? So much! We now look forward to upcoming performances, growing our membership, and expanding our musical product with new arrangements and an education component each week. It’s an exciting time to be part of this ever-growing ensemble!

Read More

Submit your own Community Post here.

Pedal with Petals Family Bike Ride

Join us on Saturday, May 11th and ride into spring during our Pedal with Petals Family Bike Ride. Back for its second year, Pedal with Petals is going to be bigger than ever. This year’s event will include both an

Encore Creativity for Older Adults at Capital One Hall

Encore Creativity for Older Adults is pleased to raise the curtain and welcome community members to its spring concert at Capital One Hall in Tysons, VA on May 4, 2024. The concert, which starts at 3 PM, will bring hundreds

×

Subscribe to our mailing list