Construction on the I-495 Express Lanes expansion in McLean is about to get a little more intense.
Work to demolish the existing Georgetown Pike Bridge over I-495 — also known as the Capital Beltway — will begin this week, potentially even today (Tuesday), the Virginia Department of Transportation announced Friday (June 17).
Contracted for the 495 NEXT project to extend the Beltway’s toll lanes from Tysons to the George Washington Memorial Parkway, workers will start by demolishing the median in the center of the Georgetown Pike bridge and installing a temporary traffic barrier on the westbound shoulder, according to the news release.
“Temporary traffic signals will be installed to enable the removal of the existing signals,” VDOT said. “East- and westbound traffic on Georgetown Pike will then be shifted south on the existing bridge.”
The changes are necessary for crews to take down the northern part of the bridge, a process expected to start in mid-July and take approximately three weeks to complete, depending on the weather and other factors.

Here is more from VDOT on what to expect:
Specialized equipment will be used to demolish the bridge, including excavators fitted with hammers, saws and hydraulic jaws. While every effort will be made to control noise, some demolition is unavoidably noisy and must be performed during nighttime hours when Beltway traffic below the bridge is lightest and necessary lane closures can occur.
Overnight triple- and double-lane closures on the Beltway and periodic stoppages of all lanes for brief intervals will be necessary to ensure the work is performed safely. Virginia State Police will implement periodic shutdowns of all lanes for up to 30 minutes. Traffic will be cleared before subsequent shutdowns take place.
Periodic lane closures will occur throughout construction during midday and overnight hours.
“Travelers approaching the Georgetown Pike Bridge should use caution, pay attention to roadway signs approaching and in the work zone, and anticipate delays and plan their trips accordingly,” VDOT said.
The bridge will be replaced by a longer, six-lane-wide span to accommodate the Beltway, which is getting two new lanes in each direction. The revamped bridge will also have a six-foot-wide sidewalk and a trail link to Scotts Run Nature Preserve, according to updated plans shared earlier this month.
VDOT has spent months slowly ramping up work on 495 NEXT, starting preliminary activities late last year before breaking ground in March. Construction in the corridor began in earnest at the beginning of June with the permanent closure of the interstate’s northbound left-shoulder lane between Old Dominion Drive and the GW Parkway.
While VDOT says the project will provide much-needed congestion relief, it has faced resistance from some residents and elected officials, most recently over plans to task Maryland with some construction work tying the new toll lanes into the new American Legion Bridge that it’s supposed to build.
Maryland transportation officials released a final environmental study for proposed express lanes on their side of the Beltway on Friday, reporting that changes to the design will reduce the project’s anticipated impact on land, streams, and trees.
Photo via Google Maps
Recent Stories

Art House 7 warmly welcomes you to our upcoming Fall 2 session of classes starting on October 30th. We’re thrilled to offer a diverse range of mediums and flexible class lengths, catering to a wide age range, starting from as young as 2, and, of course, providing a multitude of engaging options for adults!
Our classes cover an exciting spectrum of creative mediums, including fiber arts such as knitting, modern embroidery, crochet, and sewing. We also offer classes in ceramics on the wheel, drawing, watercolor, gouache, oil, acrylic, still-life painting, and captivating Japanese Suminagashi and printmaking. One of the highlights of this session is the highly anticipated 5-week “Painting the Portrait and Figure” workshop, led by the renowned local artist, Danni Dawson.
For our younger artists, we have specially designed classes like “Art Exploration through Impressionism” for students in kindergarten through 5th grade, an engaging “Art Together” parent-child class designed for 2–4-year-olds, and a “Teen Taught Art Club” tailored for kindergarteners through 4th graders.
Winter Wonderland Fundraiser
Proceeds benefit Fellowship Square, improving the lives of 800+ older adults with very limited income and resources by providing affordable housing and supportive services.
Experience a festive holiday fundraiser complete with savory wines & craft beers, scrumptious hors d’oeuvres, exciting