Simulated service for Silver Line Phase Two to begin next month but opening date uncertain

Phase two of the long-awaited Silver Line is likely slated for a late fall opening.

At a Washington Metropolitan Area Transit Authority board meeting today (Thursday), efforts are underway to complete safety and certification requirements, according to Theresa Impastato, WMATA’s executive vice president and chief safety officer.

But an exact date remains uncertain. Metro’s board will set the date for servicing the 11.4-mile extension into Loudoun County. It’s unlikely service will begin until late October, especially since simulated service that is expected to continue through mid-October.

“I know everyone in the community is dying to hear,” said WMATA’s CEO Randy Clarke, adding that the organization is entering the “red zone” towards announcing a date.

With nearly all hiring completed, onsite training is planned by September 11. Simulated service will take place between October 3 and 17, according to Lynn Bowersox, WMATA’s senior vice president.

The second phase of the Silver Line has been in the works under the Metropolitan Washington Airports Authority for almost a decade now, encountering numerous delays that have frustrated local residents, business owners, and elected officials.

The Washington Metrorail Safety Commission will then approve a safety certification when the materials are submitted in the middle of October — one of the 10 conditions of acceptance of the project.

Metro’s board will then set a date for service.