Email signup

Planned Herndon water pump will have capacity for 10M gallons a day

Herndon will work with Fairfax Water to add a pump station next to the police station (via Town of Herndon)

A pump station proposed for the Herndon Police Department site will be able to process 10 million gallons of water per day, town staff say.

The station is part of a broader retooling of Herndon’s Utility Master Plan, which outlines how the town will bolster its water infrastructure in preparation for development around the downtown and future Metro station.

Presented to the town council in 2017, that plan anticipated the town would need to increase its water capacity by an additional 1 million gallons per day by 2025. The town purchased new storage in 2018, bringing its total capacity to 5.7 million gallons per day, according to a staff report by the Herndon Department of Public Works.

However, a shift in development trends in favor of residential construction over commercial led staff to revisit its earlier estimates and conclude that a new pump station would make more sense than the previous plan to add two transmission mains.

“This would allow us to get the additional capacity that we will need in a much more economical and reliable fashion than our previous plans estimated,” Herndon Deputy Director of Public Works Tammy Chastain told the town council during a work session on Tuesday (Oct. 4).

The new pump station will be on the police station property at 397 Herndon Parkway, where it can be connected to an existing 24-inch-wide pipeline that runs parallel to the Washington & Old Dominion Trail.

The town council is slated to approve a pending agreement with Fairfax Water for the project on Tuesday (Oct. 11), kicking off the design process.

Fairfax Water would be responsible for designing, building, operating and maintaining the facility, while the Town of Herndon would cover the design and construction costs.

“They are the ones that are going to have to upgrade it and maintain it,” Chastain said. “If it needs major repairs, we’d probably be helping in funding that. It’s only for us right now, which is why we’re paying the full cost.”

Right now, the estimated cost is nearly $5 million — higher than what town officials suggested before initiating an engineering study in 2019 but lower than the over $6 million that would’ve been needed for two transmission lines, according to Chastain.

The funding will come from the federal COVID-19 relief that the town was allocated by the American Rescue Plan Act, which included water and sewer projects as a viable use of the money, Town Manager Bill Ashton confirmed.

“This is good news because we’ve been planning for this for years,” Mayor Sheila Olem said. “Unfortunately, we went through Covid, but now, we’re getting this funding for something we knew we were putting in anyway. This is great.”

The pump station is “a step amongst several” in Herndon’s utility plan, Ashton said. At some point, the town will also replace its storage tank on Alabama Drive with two smaller tanks that the pump will fill.

Since the station will be right next to the W&OD, Councilmember Sean Regan questioned how it might affect the greenery alongside the trail and whether anything will need to be replaced.

Ashton responded that the potential impact on green space is “a design consideration we would certainly look at.”

Recent Stories

A proposed commuter ferry system for the Potomac River in Northern Virginia has gained attention from regional officials, but the price tag has dampened enthusiasm. With budget shortfalls looming and…

Goodwill is launching a new express donation site in the Herndon area. The drop-off site is expected to officially open in the Village Center at Dulles sometime this month, according…

The best path forward for saving Lake Accotink might to let it shrink, a Fairfax County task force has proposed. Created by the Fairfax County Board of Supervisors in May,…

Tysons Galleria has lost another dining option. Jiwa Singapura, which sought to blend Singaporean street food with a “high-end” setting, closed its doors on Monday, Dec. 4 after less than…

Art House 7 warmly welcomes you to our upcoming Fall 2 session of classes starting on October 30th. We’re thrilled to offer a diverse range of mediums and flexible class lengths, catering to a wide age range, starting from as young as 2, and, of course, providing a multitude of engaging options for adults!

Our classes cover an exciting spectrum of creative mediums, including fiber arts such as knitting, modern embroidery, crochet, and sewing. We also offer classes in ceramics on the wheel, drawing, watercolor, gouache, oil, acrylic, still-life painting, and captivating Japanese Suminagashi and printmaking. One of the highlights of this session is the highly anticipated 5-week “Painting the Portrait and Figure” workshop, led by the renowned local artist, Danni Dawson.

For our younger artists, we have specially designed classes like “Art Exploration through Impressionism” for students in kindergarten through 5th grade, an engaging “Art Together” parent-child class designed for 2–4-year-olds, and a “Teen Taught Art Club” tailored for kindergarteners through 4th graders.

Read More

Submit your own Community Post here.

Winter Wonderland Fundraiser

Proceeds benefit Fellowship Square, improving the lives of 800+ older adults with very limited income and resources by providing affordable housing and supportive services.

Experience a festive holiday fundraiser complete with savory wines & craft beers, scrumptious hors d’oeuvres, exciting

German Christmasmarket

Join us for a festive and joyful event hosted by the German military at 11150 Sunrise Valley Drive, Reston, Virginia, USA! Experience the magic of a traditional German Christmas market, right here in the heart of Reston. Immerse yourself in

×

Subscribe to our mailing list