Fairfax County must pay MWAA another $40M for Silver Line Phase II

The Herndon Metro station (staff photo by Jay Westcott)

With the Silver Line Phase II opening still in flux, Fairfax County is being asked to pay another $40 million.

At its transportation committee meeting on Friday (Sept. 30), the Board of Supervisors got an update on the ramifications of the Metropolitan Washington Airports Authority (MWAA) agreeing in July to increase the budget for the Silver Line extension by $250 million.

The original project agreement calls for Fairfax County to pay about 16% of the asked-for overage, so with the quarter of a billion dollar budget increase, the county owes an additional $40.25 million.

All told, the county will have spent nearly a billion dollars — $960 million — on the second phase of the Silver Line, which will add six stations from Reston to Ashburn in Loudoun County.

In total, the project has cost just over $3 billion. The board is set to vote on the payment later this month.

While likely to approve the additional payment, several supervisors expressed frustration and annoyance with the need to throw even more dollars at a project that has been besieged by constant delays.

“I don’t think it’s a shock and it’s a tiny portion of the overall project,” Chairman Jeff McKay said. “But [the extra $40 million] has rightly angered a lot of folks given all the delays.”

Dranesville District Supervisor John Foust also made clear he was not happy that the county is being asked to pay more.

“Have we asked ourselves if this is a good deal and the Airports Authority is not just…spending a lot of money to make a problem go away? And it’s our money that they are spending,” Foust asked staff.

He also asked if $960 million will be the final amount. However, county staff couldn’t guarantee that there won’t be any further costs, considering Phase 1 is still undergoing repairs after opening in 2014.

“We still have to reconcile Phase 1 and Phase 2…All parties have to be reconciled at the end of the project,” said Martha Elena Coello, head of special projects for the Fairfax County Department of Transporation. “We are still doing some work on Phase 1 and that needs to be completed. At the end, there will be a reconciliation of both those phases.”

McKay asked, seemingly rhetorically, what would happen if the county didn’t pay the extra money. Staff responded that it might become a “legal matter” since the payment is required by the signed project agreement.

“According to the funding agreement, this is not a ‘might be’ or ‘may be,'” he said. “It’s a requirement for the county. We don’t have the flexibility…without significant negative consequences.”

Still relatively new Metro General Manager Randy Clarke was given authority by the Board of Directors last month to set an opening date for the Silver Line extension. While no exact date has been announced, Clarke said safety certifications are expected this October, and Metro has updated its maps to feature the new stations.

At the same time, Clarke warned that opening the Silver Line could force service reductions due to a deficit in trains when currently shuttered Blue and Yellow Line stations south of Washington National Airport reopen.

That headache will be put off a little longer by an entirely different Metro problem. Last week, the transit agency announced that its new Potomac Yard station won’t open until 2023. As a result, the Yellow and Blue stations will be closed for another two weeks, until Nov. 5.

Recent Stories

Good Friday evening, Fairfax County. Let’s take a look back at today’s stories and a look forward to tomorrow’s event calendar. đź•— News recap The following articles were published earlier…

For this year’s Independent Bookstore Day, local bookworms will be encouraged to collect not just new literary titles, but also places to buy them. More than a dozen shops across…

The Oakton driver behind a 2022 crash that killed two teenagers has been sentenced to four years in prison. Earlier this week, 20-year-old Usman Shahid was convicted of two counts of…

RELAC Water Cooling will begin delivering air-conditioning services to residents and businesses in Reston’s Lake Anne area this weekend — ahead of its official launch date of May 22. The…

The Gillion Academy’s Home School Basketball Program begins Fall 2024 for 7th – 12th Grade student-athletes to complete their online academic studies in a supervised and focused setting while receiving elite training from our professional basketball trainers at The Gillion Basketball Academy, a state of the art training facility in Springfield, Va. We have developed over 200 college athletes and placed over 50 players in the NBA and pro leagues overseas and provide the same level of training for our student-athletes.

We will have a virtual Open House Zoom on May 6th at 7:30PM so please go to our website to learn more about us and to fill out an interest form and register for the event and learn about the top training facility in the DMV area.

Any questions please email our Director at philip.budwick@gil-lionbasketballacademy.com.

Read More

Submit your own Community Post here.

For many remote workers, a messy home is distracting.

You’re getting pulled into meetings, and your unread emails keep ticking up. But you can’t focus because pet hair tumbleweeds keep floating across the floor, your desk has a fine layer of dust and you keep your video off in meetings so no one sees the chaos behind you.

It’s no secret a dirty home is distracting and even adds stress to your life. And who has the energy to clean after work? That’s why it’s smart to enlist the help of professionals, like Well-Paid Maids.

Read More

Submit your own Community Post here.

Pedal with Petals Family Bike Ride

Join us on Saturday, May 11th and ride into spring during our Pedal with Petals Family Bike Ride. Back for its second year, Pedal with Petals is going to be bigger than ever. This year’s event will include both an

Encore Creativity for Older Adults at Capital One Hall

Encore Creativity for Older Adults is pleased to raise the curtain and welcome community members to its spring concert at Capital One Hall in Tysons, VA on May 4, 2024. The concert, which starts at 3 PM, will bring hundreds

Ă—

Subscribe to our mailing list