Fairfax County wants to figure out why approved housing isn’t getting built

A construction crane behind the vacant office building at 1831 Wiehle Avenue in Reston, a site approved for mixed-use residential redevelopment (staff photo by Angela Woolsey)

The Fairfax County Board of Supervisors directed staff on Tuesday (Nov. 17) to explore ways to aid developers whose housing projects have been approved but remain unbuilt.

The proposal asks staff to see where the county can “influence what is in our control” in terms of the development process to make it easier to advance or revise plans stalled following county approval, said Board Chair Jeff McKay, who introduced the board matter with Vice Chair Kathy Smith (Sully District).

How many residential units are currently stuck in limbo? Springfield District Supervisor Pat Herrity estimated that “there’s at least 40,000,” though county staff is working to tabulate a concrete figure.

The reasons why housing projects may be held up vary, and “many of them are outside our control,” McKay acknowledged, pointing to elevated interest rates and higher construction costs as prime examples.

But there are areas where the county government can help. One way would be to expedite the process when a developer needs to ask county officials for permission to amend its development agreement reached with the county.

County staff doesn’t have the power to amend so-called proffer agreements, which must return to the Board of Supervisors for action. Several supervisors said the timetable for accomplishing that can be improved.

“This process could be more streamlined,” said Hunter Mill District Supervisor Walter Alcorn, who estimated there are 15,000 residential units in Reston and other parts of his district that have been approved but not constructed.

Another area that might see change is the issuance of building permits.

Currently, projects must begin construction within six months of issuance, or the permit expires. The package of proposals adopted on Nov. 17 calls on building officials to use their powers to grant extensions “when it makes sense and can advance housing construction.”

The directive also asks county staff to reach out to developers to determine what is holding up their projects.

A broader survey of factors contributing to delays or a lack of action on approved housing projects is set to be undertaken by the auditor to the Board of Supervisors. A report is expected to be released early next year, around the same time staff have been directed to give the board an update on their ongoing efforts.

About the Author

  • Scott McCaffrey

    A Northern Virginia native, Scott McCaffrey has four decades of reporting, editing and newsroom experience in the local area plus Florida, South Carolina and the eastern panhandle of West Virginia. He spent 26 years as editor of the Sun Gazette newspaper chain. For Local News Now, he covers government and civic issues in Arlington, Fairfax County and Falls Church.