Dominion Energy to begin prep work on undergrounding Tysons power line

Tysons to Spring Hill transmission line construction phases (via Dominion Energy)

(Updated at 12:15 a.m. on 4/27/2023) Preliminary construction activities will kick into gear this weekend on a long-gestating project to move part of an electric transmission line underground in the Spring Hill area of Tysons.

Starting this Friday (April 28) evening, Dominion Energy will close the Vesper Trail from Route 7 (Leesburg Pike) to Vesper Street so its crews can install a manhole needed for the project, spokesperson Peggy Fox said. The trail closure will last until Tuesday (May 2).

“This closure is necessary to keep community members safe while we install a manhole,” Fox told FFXnow.

Replacing an existing above-ground line, the new 230-kilovolt transmission line will span approximately half a mile from Dominion’s Tyco Road substation to the vicinity of a planned Spring Hill substation just southwest of Leesburg Pike and Spring Hill Road.

An underground line will be safer and less visually obtrusive, while helping Tysons meet the demand for electricity as the area continues to develop, Dominion has said. Removal of the existing overhead line will also “facilitate” construction on The View, a mixed-use development planned next to the Spring Hill Metro station, according to documents filed with the State Corporation Commission.

The project was endorsed by the Fairfax County Board of Supervisors in March 2020 and approved by the SCC on June 24, 2021.

Dominion notified residents in the area on April 14 that construction on the power line would begin this month, noting that the county has waived noise restrictions for the project until Oct. 31 since some work will occur at night.

“To limit traffic impacts on major roadways, particularly Leesburg Pike, construction will be performed at night,” the utility company said. “This allows our crews to obtain necessary lane closures to complete the work safely and efficiently.”

Split into five phases, the project includes the installation of two manholes, which will occur throughout the day and night so they can be completed “as expeditiously as possible.”

“There will be more impacts to the trail in fall 2023 when we begin installing the underground line in this area, and outreach will take place prior,” Fox said by email. “No impacts to electric service are anticipated as a result of this work.”

Including the addition of a transition pole at the end of the new line and removal of the old overhead line, the project is expected to finish in late 2024. At that point, Dominion says it will begin construction on the Spring Hill substation, which will occupy a 1-acre site near Raglan Road Park.

The new substation will support customers south of Route 7 (Leesburg Pike) and outside of I-495, according to Dominion.

Recent Stories

Morning Notes

Sentencing of Driver in Fatal Oakton Crash Delayed — “The sentencing hearing in the manslaughter case of two Oakton High School students killed in a June 7, 2022, crash abruptly stopped…

Good Thursday evening, Fairfax County. Let’s take a look back at today’s stories and a look forward to tomorrow’s event calendar. đź•— News recap The following articles were published earlier…

Nearly 14 years after Clifton Elementary School shuttered, its sign has been repurposed. The sign now serves as a bulletin for local organizations, businesses, and community groups to promote events…

The Spring Hill Rec Center in McLean is now being partly powered by the sun. The Fairfax County Park Authority announced today (Thursday) that it has turned on a new, 307-kilowatt…

The Gillion Academy’s Home School Basketball Program begins Fall 2024 for 7th – 12th Grade student-athletes to complete their online academic studies in a supervised and focused setting while receiving elite training from our professional basketball trainers at The Gillion Basketball Academy, a state of the art training facility in Springfield, Va. We have developed over 200 college athletes and placed over 50 players in the NBA and pro leagues overseas and provide the same level of training for our student-athletes.

We will have a virtual Open House Zoom on May 6th at 7:30PM so please go to our website to learn more about us and to fill out an interest form and register for the event and learn about the top training facility in the DMV area.

Any questions please email our Director at philip.budwick@gil-lionbasketballacademy.com.

Read More

Submit your own Community Post here.

For many remote workers, a messy home is distracting.

You’re getting pulled into meetings, and your unread emails keep ticking up. But you can’t focus because pet hair tumbleweeds keep floating across the floor, your desk has a fine layer of dust and you keep your video off in meetings so no one sees the chaos behind you.

It’s no secret a dirty home is distracting and even adds stress to your life. And who has the energy to clean after work? That’s why it’s smart to enlist the help of professionals, like Well-Paid Maids.

Read More

Submit your own Community Post here.

Pedal with Petals Family Bike Ride

Join us on Saturday, May 11th and ride into spring during our Pedal with Petals Family Bike Ride. Back for its second year, Pedal with Petals is going to be bigger than ever. This year’s event will include both an

Encore Creativity for Older Adults at Capital One Hall

Encore Creativity for Older Adults is pleased to raise the curtain and welcome community members to its spring concert at Capital One Hall in Tysons, VA on May 4, 2024. The concert, which starts at 3 PM, will bring hundreds

Ă—

Subscribe to our mailing list