The Boro developers appeal county’s claim that construction blocked pedestrian access

Construction on the next phase of The Boro in Tysons has prevented pedestrians from safely walking on the streets around the site, a Fairfax County inspector says.

Matthew Stenger, an investigator with the county’s Department of Code Compliance, issued violation notices last month against The Meridian Group, The Boro’s master developer, and Silverstone Silver Living, which is constructing The Trillium Tysons, a senior living building expected to open this year.

A Nov. 15 inspection of the construction site bounded by Westpark Drive to the south and Greensboro Drive to the east “revealed that there is no safe and efficient pedestrian pathway provided along the properties street frontages,” Stenger said in the Dec. 15 notices.

The code compliance investigator also alleged that the companies failed to submit a construction management plan required as a condition of the expansion project’s approval in 2021.

Both developers have now separately filed appeals challenging the citations, stating that they have in fact provided the promised plan, which shows that a sidewalk on the southbound side of Westpark Drive would be closed throughout construction.

“Sidewalk closures are specifically identified as an appropriate method to ensure pedestrian safety,” Silverstone’s zoning appeal says. “…After consultation with County staff, due to existing sensitive fiber optics and live power infrastructure…along the Block J frontage, it was agreed that no safe interim pedestrian pathway was possible and a closure of the southbound side sidewalks during construction was necessary.”

Block J — The Trillium — is one of four blocks planned for The Boro’s expansion to the west side of Westpark Drive. Under construction since spring 2022, the apartment building for seniors will eventually be joined by two multi-family residential buildings with retail and either a health club or townhouses.

During the county’s review of plans for the development, nearby residents raised concerns about its accessibility and potential construction impacts, which led Meridian and Silverstone to agree to provide a construction management plan.

In addition to raising the possibility of fines, the code compliance department directed the developers to submit the required plan and build temporary pedestrian facilities along Greensboro and Westpark.

“Within two weeks after the date of this notice, you must complete the installation of an asphalt path along the Greensboro frontage,” Stenger wrote. “Within three weeks of the date of this Notice, you must complete the installation of that asphalt trail down Westpark Drive as close to the frontage of Block J as possible.”

However, Silverstone says in its appeal that construction on the Westpark trail — which will represent the first segment of the planned Tysons Community Circuit — can’t begin until Dominion Energy relocates its electrical utilities, a process expected to be complete this January.

Even after the utilities are moved, a temporary sidewalk can’t be safely built “due to the required installation and coordination of tree pits, bio filters, and additional underground infrastructure along the street,” Walsh Colucci land use attorney Lynne Strobel wrote in a statement on the developer’s behalf.

In a separate appeal application, The Meridian Group noted that the proposed temporary sidewalk on Westpark Drive would lead “pedestrians to a dead end at an active construction site,” which could result in people crossing the road without a crosswalk or traffic signal.

“The appropriate solution is to direct pedestrians to cross Westpark Drive at its intersection with Greensboro drive to access the existing sidewalk on the northbound side of Westpark,” Strobel wrote. “…The suggested sidewalk should only be constructed when the pedestrian signal at Boro Place is operational.”

According to the application, construction is underway on sidewalks along Clover and Broad streets, and the developer has agreed to build a temporary asphalt sidewalk on Greensboro. All of the facilities are on track to be completed and open for use “within the next several weeks,” as of mid-December.

A public relations firm representing The Meridian Group said the developer has no comment on its appeal.

Meridian and Silverstone have asked the county to dismiss the notices of violations, saying they’re “based on incorrect and inaccurate facts.”

Recent Stories

Good Friday evening, Fairfax County. Let’s take a look back at today’s stories and a look forward to tomorrow’s event calendar. 🕗 News recap The following articles were published earlier…

For this year’s Independent Bookstore Day, local bookworms will be encouraged to collect not just new literary titles, but also places to buy them. More than a dozen shops across…

The Oakton driver behind a 2022 crash that killed two teenagers has been sentenced to four years in prison. Earlier this week, 20-year-old Usman Shahid was convicted of two counts of…

RELAC Water Cooling will begin delivering air-conditioning services to residents and businesses in Reston’s Lake Anne area this weekend — ahead of its official launch date of May 22. The…

The Gillion Academy’s Home School Basketball Program begins Fall 2024 for 7th – 12th Grade student-athletes to complete their online academic studies in a supervised and focused setting while receiving elite training from our professional basketball trainers at The Gillion Basketball Academy, a state of the art training facility in Springfield, Va. We have developed over 200 college athletes and placed over 50 players in the NBA and pro leagues overseas and provide the same level of training for our student-athletes.

We will have a virtual Open House Zoom on May 6th at 7:30PM so please go to our website to learn more about us and to fill out an interest form and register for the event and learn about the top training facility in the DMV area.

Any questions please email our Director at philip.budwick@gil-lionbasketballacademy.com.

Read More

Submit your own Community Post here.

For many remote workers, a messy home is distracting.

You’re getting pulled into meetings, and your unread emails keep ticking up. But you can’t focus because pet hair tumbleweeds keep floating across the floor, your desk has a fine layer of dust and you keep your video off in meetings so no one sees the chaos behind you.

It’s no secret a dirty home is distracting and even adds stress to your life. And who has the energy to clean after work? That’s why it’s smart to enlist the help of professionals, like Well-Paid Maids.

Read More

Submit your own Community Post here.

Pedal with Petals Family Bike Ride

Join us on Saturday, May 11th and ride into spring during our Pedal with Petals Family Bike Ride. Back for its second year, Pedal with Petals is going to be bigger than ever. This year’s event will include both an

Encore Creativity for Older Adults at Capital One Hall

Encore Creativity for Older Adults is pleased to raise the curtain and welcome community members to its spring concert at Capital One Hall in Tysons, VA on May 4, 2024. The concert, which starts at 3 PM, will bring hundreds

×

Subscribe to our mailing list