A key regional transportation panel seems to be leaning in the direction of running the future bus rapid transit (BRT) line on the eastern side of Route 7 using curb lanes, rather than in the roadway’s center.
“We see benefits to more riders” by going the curbside option, Northern Virginia Transportation Commission (NVTC) senior planner Vikram Sinha said at a Nov. 16 community forum in Bailey’s Crossroads.
Putting bus stops in the center of the road would reduce travel times for passengers taking the route for longer distances, he said, but it would not help riders making shorter journeys.
Sinha’s comments came as he detailed results of a lengthy evaluation of options for how the Route 7 BRT could operate from Seven Corners to Southern Towers and/or the Mark Center in Alexandria.
It is the easternmost portion of a planned, 14-mile Route 7 BRT system that would start at the Spring Hill Metro station in Tysons. The network would then run east through portions of three jurisdictions — Fairfax County, Falls Church and Alexandria — using roadway owned by the two cities and the Virginia Department of Transportation (VDOT) for the Fairfax County sections.
For the Seven Corners-to-Alexandria section, both curbside bus loading and center-island loading would reduce travel times for buses compared to the current situation, where buses share travel lanes with other vehicles, according to NVTC’s traffic analysis.
But curbside passenger loading likely could be accomplished with less need to acquire expensive right-of-way and had the support of a majority of riders surveyed over the past year.
While curb-running buses might require a reduction in travel lanes, they would have fewer negative impacts on intersections and “can potentially be implemented faster and at less cost” in some portions of the route, Sinha said at yesterday’s meeting, held at Bailey’s Elementary School for the Arts and Sciences.
With no current funding identified for the project, local governments, VDOT and regional bodies have time to consider their options. Sinha said there would be “an opportunity to mix and match” different approaches in different areas of the route.
“What would work in Fairfax County might not work in Falls Church, and vice versa,” he said.
Though unlikely to be as expensive as the nearly $1 billion BRT project known as “The One” being developed for Fairfax’s Route 1 corridor, the cost of the Route 7 BRT project will run into the hundreds of millions of dollars, no matter which design options are selected.
It will be part of what regional leaders hope will become a growing network of BRT lines aimed at getting people out of their own vehicles and onto faster, more convenient transit.
In addition to representatives from VDOT, the Fairfax County Department of Transportation and Virginia Department of Rail and Public Transportation, the officials on hand at yesterday’s community meeting included Fairfax County Supervisors Walter Alcorn (Hunter Mill District) and Jimmy Bierman (Dranesville).
Both men are NVTC board members. Bierman chairs the county supervisors’ transportation committee, and Alcorn represents Northern Virginia on the board of the Washington Metropolitan Area Transit Authority.

The Route 7 corridor is home to about 40 separate bus routes, including Metrobus and local systems like Fairfax Connector. The primary transit provider is Metro’s F20 line, Virginia’s busiest bus route with more than 2 million trips per year.
On Dec. 14, Metro will introduce limited-stop F2X service to the corridor, with even shorter times between buses.
“We’re hoping this new service can meet some of the upcoming demand,” Sinha said.
With the additional service, bus frequency in the corridor is expected to decline to just six minutes.
NVTC’s Envision Route 7 study of future transit options in the Route 7 corridor from Tysons to Alexandria began in 2013, with analysis of alternatives starting four years later.
That analysis determined that a BRT approach would best serve riders and cost less than a light-rail system.
The Fairfax County Department of Transportation (FCDOT) in 2021 released its own evaluation of options along portions of the route inside the county, to determine optimal routing. That report agreed that bus rapid transit would be an effective tool for the corridor.
“BRT ridership and experience are comparable to light rail, but with lower capital costs,” Fairfax officials said in the 2021 report.